lisasolace
2006-12-01 18:44:11 UTC
We've been working as a scrum team for almost two years now, and the
one thing that continually ticks me off is that at the end of the
sprint, we end up punting all those items that were barely limping
along during the sprint, just so we can look like we're done with the
items in our backlog.
We are a content development team that works on a continuous
publishing basis (releasing various pieces of content about once a
month) and we don't always control our destiny when it comes to
having control over our backlog. Another side-effect is that writers
are notoriously bad at predicting work load. We've tried adding in
buffers to account for our ever-growing sprint backlog - but
inevitably, we don't bump items back into the product backlog until
we see that it's absolutely hopeless 5 days before the end of the
sprint. I know I could draw a hard line and force the issue, but that
makes the team extremely distressed. So many times, they've been
heros and been able to get more work (albeit different work than
planned) done in a typical sprint.
Am I just making too much out of meeting the goals we have planned -
even if we've planned equal amounts of work? Does it really matter
since we don't really need to hand off a completed product at the end
of a sprint?
one thing that continually ticks me off is that at the end of the
sprint, we end up punting all those items that were barely limping
along during the sprint, just so we can look like we're done with the
items in our backlog.
We are a content development team that works on a continuous
publishing basis (releasing various pieces of content about once a
month) and we don't always control our destiny when it comes to
having control over our backlog. Another side-effect is that writers
are notoriously bad at predicting work load. We've tried adding in
buffers to account for our ever-growing sprint backlog - but
inevitably, we don't bump items back into the product backlog until
we see that it's absolutely hopeless 5 days before the end of the
sprint. I know I could draw a hard line and force the issue, but that
makes the team extremely distressed. So many times, they've been
heros and been able to get more work (albeit different work than
planned) done in a typical sprint.
Am I just making too much out of meeting the goals we have planned -
even if we've planned equal amounts of work? Does it really matter
since we don't really need to hand off a completed product at the end
of a sprint?